Church Street Stormwater Catchment Upgrade

Project Details:

Project Name:
Church Street pipe upgrade
Proposed Status:
Complete
Previous Status:
Construct in 2020/21
Proposed Budget:
$350,000
Project Objective:
Asset upgrade
Project Justification:
The objective of this project is to reduce the risk of flooding and  mitigate against sea level increases by improving the stormwater network in this catchment
Project Scope: 
The aim is to increase capacity of existing system through the construction of existing stormwater lines in Church Street. It is proposed to upgrade the line including installation of new manholes and detention basin.

Project Photos: