Project Name:                     Victory Avenue Kerb Renewal

Proposed Status:                Construct in 2019-20

Previous Status:                  No change

Proposed Budget:              $210,000

Project Objective:              Asset renewal

Project Justification:         The seal and kerb assets are in poor condition and require renewal

Project Scope:                     It is proposed to renew the kerb on each side of the road and reseal the road. Subsoil drains will be installed where possible and minor drainage improvements may be required.  The project may include a continuation of the scheme of road humps at each end of the street as is being constructed in the adjacent Adelaide Street