Project Name:                     Stormwater Outfall Risk Management

Proposed Status:                Construction in 2019-20 (and annually)

Previous Status:                  No change

Proposed Budget:              $20,000

Project Objective:              Risk management (public and Council personnel) and operational efficiency

Project Justification:         Minimise flooding areas through increasing outtake of stormwater capacity.

Project Scope:                     Works is identified throughout the year from asset inspections and public requests