Spreyton Primary School Crossing

Project Name:                    Spreyton Primary School Crossing

Proposed Status:               Construct in 2020/21

Previous Status:                 No change

Proposed Budget:              $104,000 (seeking 100 % funding from VRU program)

Project Objective:              Asset upgrade – safety

Project Justification:        Mersey Road is a major arterial road with increasing traffic volumes. Traffic queues occur around the school entry and crossing at start and finish of school day. Travelling by car to school has a significant impact on traffic congestion

Project Scope:                  Re-aligning kerb and removing parking close to crossing and increasing the size of the school crossing islands. Installing the right turn lane for the school car park