Kiah Place – Playground equipment renewal

Project Name:                     Kiah Place – Playground equipment renewal

Proposed Status:               Construct in 2020/21

Previous Status:                 No change

Proposed Budget:              $78,000 from Federal Government’s Drought Impact Program

Project Objective:              Asset Renewal

Project Justification:     This playground was installed in 1996 and is far beyond its nominal useful life of 10 years.  Steel components were repainted in 2015 but the critical elements have now reached end of life

There has been conjecture about whether a playground is required at this location.  However, engagement with the East Devonport Special Interest Group and the local community has confirmed that there is demand for a playground in this location.  Volunteers have initiated a project to rejuvenate the areas surrounding the playground

Project Scope:                  Replace playground equipment to an equivalent scope.

 

Current Works & Projects

Bluff Headland – Handrail replacement and extension

The southern part of the path has a handrail, but a risk assessment has recommended that the handrail be extended to reduce the risk of falls. In addition, the existing handrail is approaching end of life and should be renewed at the same time.

Read More →
Current Works & Projects

298 Bellamy Road stormwater improvements

The project involves construction of new headwalls both upstream and downstream and extend the pipe downstream.

Read More →
Current Works & Projects

Mersey Main Road Stadium Crossing

Existing refuge island is inadequate to protect vulnerable road users as they attempt to cross busy Mersey Main Road against a peak traffic volume of 14,000 vehicle per day.

Read More →