Girdlestone Park Lighting Upgrade

Project Name:                     Girdlestone Park Lighting Upgrade

Proposed Status:               Construction in 2020/21

Previous Status:                 No change

Proposed Budget:              $228,774 (100 % funded by a Federal Government grant)

Project Objective:              Asset renewal

Project Justification:      The East Devonport Football Club was successful in securing a grant for this much needed renewal project

Project Scope:                  The project involves the design and construction of lighting to regional
training specifications, an upgrade of the power supply to 200amp capacity, decommissioning of the existing lighting infrastructure and relocation of the current infrastructure from the existing light poles to the new poles

 

Current Works & Projects

Bluff Headland – Handrail replacement and extension

The southern part of the path has a handrail, but a risk assessment has recommended that the handrail be extended to reduce the risk of falls. In addition, the existing handrail is approaching end of life and should be renewed at the same time.

Read More →
Current Works & Projects

298 Bellamy Road stormwater improvements

The project involves construction of new headwalls both upstream and downstream and extend the pipe downstream.

Read More →
Current Works & Projects

Mersey Main Road Stadium Crossing

Existing refuge island is inadequate to protect vulnerable road users as they attempt to cross busy Mersey Main Road against a peak traffic volume of 14,000 vehicle per day.

Read More →