Project Name:                     Forbes Street Overpass – West Side Guard Rail Works

Proposed Status:                Construction in 2019-20

Previous Status:                  No change

Proposed Budget:              $11,000

Project objective:              Provide a safe and compliant guard rail

Project Justification:        A lack of barrier terminals was identified as a medium risk in a 2013 Asset Inspection Report.  Most other risks identified in this report have been addressed

Project Scope:                     Install 2 new terminals.  It is likely that this project would be delivered in conjunction with the proposed adjacent pavement renewal project