Project Name:                     Curr Street New Footpath – West Side

Proposed Status:                Construct in 2019-20

Previous Status:                  No change

Proposed Budget:              $28,000

Project Objective:              Provide facilities as per Pedestrian Strategy 2016-2021

Project Justification:       The footpath is in a very high walkability area. This project enables the completion of the missing link and provides a safer access path

Project Scope:                    It is proposed to construct 37m of new path on the northern end plus 4 new ramps (2 at each end) to comply with DCC standards