Project Name:                     Coles Beach Road – New Pit

 Proposed Status:                Construct in 2019-20

Previous Status:                  No change

Proposed Budget:              $10,000

Project Objective:              Improve roadside drainage for road safety, protecting the pavement asset.

Project Justification:         Frequent ponding and rutting on road edge. The construction of the new pit will ensure no further road damage and provide safe access to vehicles.

Project Scope:                     New pit over existing line on south side of road and some regrading of the existing open drain to suit (refer to RDS16.0429)