Project Name:                     Coastal Pathway Lighting – Aitkenhead Point to Skate Park

Proposed Status:                Construction in 2019-20

Previous Status:                  Stage 3 in 2019-20, Stage 4 in 2020-21

(i.e. stage 4 brought forward by 1 year and combined with stage 3

Proposed Budget:              $150,000

Project Objective:              Improve safety and amenity for pedestrians and cyclists along shared path

Project Justification:         This project is to continue installation of path lighting between Roundhouse Park and the Bluff Lighthouse. Public feedback has been very positive with the first two stages constructed in years 2017-18 and 2018-19.

The project was planned to be done in 5 stages over 5 years to complete the lighting from Roundhouse Park to the Bluff Lighthouse. Comments from path users and user groups show a desire to have the link to the Surf Club completed sooner rather than later so it is proposed to complete both stage 3 and 4 in the 2019-20 financial year.

Project Scope:                 Installation of path lighting from Aitkenhead Point to Skate Park, completing the link from Roundhouse Park to the Surf Club.